The first power barge to proÂduce 225 megawatts of elecÂtricity to alleviate the rolling power cuts is expected to set sail to Ghana toÂmorrow after a brief commissionÂing ceremony.
According to the initial arrangeÂment, the barge was scheduled to set sail yesterday but had to be reschedÂuled to tomorrow (Tuesday).
Related: > Dumsor to End Power barges will arrive next month- Power Ministry
Government officials and seÂlected media practitioners are in Turkey for the official commissionÂing ceremony before the barge sets sail.
When the vessel finally docks in Ghana, another vessel is also exÂpected to dock close to the power barge to supply it with fuel. This vessel will fuel the barge until such a time a fuel pump is connected for the barge.
A source close to the Power Ministry said Karpowership, the comÂpany that built the barge, has test fired it, and everything is functionÂing efficiently.
Related: > Dumsor promises Arrival of Karpower barges postponed
Under normal circumstances, the journey from Turkey to Ghana should take 21 days (three weeks).
However, The Finder understands that considering the urgency of the situation, a fast boat, called a Semi- submersible vessel, has been conÂtracted to pull the barge for it to arrive in Ghana in two weeks.
Government has also instructed Karpowership to increase the capacÂity of the second barge from the iniÂtial 225 megawatts to 400 megawatts.
This means government has inÂcreased the power expected from the two barges by an additional 175 megawatts, from the initial 450 megawatts to 625 megawatts.
Related: > Dumsor wahala GNPC provides guarantee for first power ship
Officials told The Finder that when the barge arrives, it would take about two weeks to connect it to the national grid.
Ground works at the location where the power barge would dock in Tenia is expected to be completed by the end of this month.
The second barge to produce 400MW is expected to be delivered by the end of the first quarter of 2016.
The power barges were originally scheduled to dock at Tema Port in the first quarter of this year.
It was rescheduled to September 2015, but government failed to meet the first two timelines for the arrival of the barges.
The first contractual 225 megawatts power ship was schedÂuled to be delivered in Ghana in September this year, and the second one was to be subjected to clarificaÂtion but will be delivered at least 60 days earlier than contracted, KarÂpowership told journalists who went to Turkey to witness progress of work on the barges.